Sewer Lift Stations
MCB, Camp Pendleton, CA
Design-Build
Repair/Replacement
$8.3 million |
|
The sewer lifts in this project have experienced spills and/or overflows in the past. The objective is to effect repairs to greatly reduce the probability of overflows & spills at the sewer lift stations. Each station has a different scope of work.
The 13 stations locations are:
LS 210583 (south end bath house) - south end of Del Mar Beach
LS 21537 (main sewage lift station) - Boat Basin Road
LS 310924 (land craft air cushion [LCAC] complex) - Third Street, west of Interstate 5
LS 31334 (marine corps support systems tactical activity) - parking lot near Bldg 31329
LS 31520 (big edison) - Stuart Mesa Road & Third Street
Ejector Station 31772 (edson pistol range) - adjacent to Range Road B
LS 520600 (motor transport) - off Basilone Road
LS 520830 (STP 11 effluent) - Basilone Road & San Mateo Road
LS 520830A (STP 11 effluent circulation) - Basilone Road & San Mateo Road
LS 2229 (warehouse) - Chappo Area
LS 2250 (salvage ejector station) - adjacent to Bldg 2251
LS 2268 (Vandergrift Blvd) - Chappo Area across from Bldg 2261
LS 2269 (old bakers) - Chappo Area across from Bldg 2261 |
|
 |